Castro / 2025-12-19/

test input parameter file: Castro-tests.ini

combined build time for all tests: 910.9457974433899 s

wall clock time for all tests: 269.5658059120178 s

Git update was done at: 2025-12-19 00:10:02 PST

 

test namedimcompare plotfile# levelsMPI procsOMP threadsOpenACCdebugcompilerestartbuild timewall timeresult
Dust-1d1
Dust-1d_plt00169
185.767 s0.090 sPASSED
Dust-2d-M2
Dust-2d-M_plt00010
1✓ (4)109.334 s1.462 sPASSED
Dust-2d-M-restart2
Dust-2d-M-restart_plt00010
1✓ (4)0.878 s2.500 sPASSED
Dust-2d-P2
Dust-2d-P_plt00020
3✓ (4)0.866 s14.986 sPASSED
Dust-3d-M3
Dust-3d-M_plt00010
1✓ (4)130.402 s4.885 sPASSED
Dust-3d-M-restart3
Dust-3d-M-restart_plt00010
1✓ (4)✓ (2)125.507 s7.580 sPASSED
Dust-3d-P3
Dust-3d-P_plt00008
3✓ (4)0.888 s162.157 sPASSED
Sedov-2d2
Sedov-2d_plt00130
469.533 s4.328 sPASSED
Sod-13
Sod-1_plt00034
3✓ (2)82.462 s14.950 sPASSED
Sod-1d1
Sod-1d_plt00034
3✓ (2)70.598 s0.485 sPASSED
Sod-23
Sod-2_plt00034
3✓ (2)75.714 s13.856 sPASSED
Sod-2d2
Sod-2d_plt00034
3✓ (2)75.980 s0.680 sPASSED
Sod-33
Sod-3_plt00034
3✓ (2)✓ (2)82.285 s15.223 sPASSED
Sod_restart3
Sod_restart_plt00034
3✓ (2)✓ (2)0.732 s26.384 sPASSED